Pennyhill Park Hotel

Pennyhill Park Hotel

Scope of Works

Scope of Works

Powells was appointed to deliver the full interior refurbishment of the terrace wing at Pennyhill Park Hotel in Bagshot, Surrey, an award-winning 5-star retreat and part of the prestigious Exclusive Collection. Our remit included the creation of a luxurious wedding venue, new conference suites on the upper level, and an outdoor terrace overlooking the landscaped gardens.

Key design features included the installation of a bespoke retractable marble staircase in the main lobby — a standout element engineered with remote-controlled telescopic steps and integrated wheelchair platform to ensure accessibility while maintaining visual elegance.






Client

Exclusive Collection

Scope of work

/

Hospitality

/

Leisure

Timeline

20 Weeks

Scope of Works

Powells was appointed to deliver the full interior refurbishment of the terrace wing at Pennyhill Park Hotel in Bagshot, Surrey, an award-winning 5-star retreat and part of the prestigious Exclusive Collection. Our remit included the creation of a luxurious wedding venue, new conference suites on the upper level, and an outdoor terrace overlooking the landscaped gardens.

Key design features included the installation of a bespoke retractable marble staircase in the main lobby — a standout element engineered with remote-controlled telescopic steps and integrated wheelchair platform to ensure accessibility while maintaining visual elegance.






Client

Exclusive Collection

Scope of work

/

Hospitality

/

Leisure

Timeline

20 Weeks

Challenges

Challenges

Challenges

  • Structural Discoveries: Unexpected structural weaknesses were uncovered around the terrace roof, necessitating a complete reconstruction and installation of new steel support frameworks.

  • Material Delays: Original roof tiles sourced from Turkey became unavailable due to a major earthquake that destroyed the factory. We rapidly procured suitable alternatives through our extensive supply network without impacting the schedule.

  • Non-Negotiable Deadline: The first wedding at the venue was confirmed before works began, requiring an uncompromising completion date. Despite the tight programme and late-stage surprises, the project was delivered on time.

Key Results

Key Results

Key Results

  • Transformed a period terrace wing into a high-end events and conferencing destination within a live luxury hotel environment.

  • Delivered on schedule despite critical challenges, ensuring the client’s wedding event proceeded seamlessly.

  • Reinforced Powells’ longstanding relationship with Exclusive Collection, leading directly to further secured projects, including South Lodge Hotel in Horsham.

Have a space in mind?

By submitting, you agree to our Terms and Privacy Policy.

Let’s
talk.

Planning a new space? We bring clarity and delivery to fit-outs of all shapes and sizes.

Have a space in mind?

By submitting, you agree to our Terms and Privacy Policy.

Let’s
talk.

Planning a new space? We bring clarity and delivery to fit-outs of all shapes and sizes.

Have a space in mind?

By submitting, you agree to our Terms and Privacy Policy.

Let’s
talk.

Planning a new space? We bring clarity and delivery to fit-outs of all shapes and sizes.